Gilroy extends its pause on new data centers to September 2027

SFBAYHCC News Desk · Oct 27, 2026

Residents came to the Gilroy City Council meeting on Monday, October 19, to speak in support of extending a temporary ban on new data centers, San José Spotlight reported. One resident told the Spotlight that the extension gives him hope, but that he questions whether the city will look after the community's interests. "It's important that we think about how we're going to work together with (Amazon Web Services) rather than working for them, which I think we are setting ourselves up to do right now," he said.

The council then voted unanimously, the Spotlight reported, to extend the moratorium it first adopted on September 14 for 10 months and 15 days from October 19, through September 3, 2027.

"The goal is to further enhance protections to public health, infrastructure and neighborhood quality of life by addressing issues such as electricity demand, water use, generator emissions, noise and traffic," City Administrator Matt Morley told the Spotlight.

What the council decided

The extension is an interim urgency ordinance under state law, Government Code section 65858. The staff report, from City Administrator Matt Morley, submitted by Community Development Director Sharon Goei and prepared by Planning Manager Michael Fossati, asked the council to:

  • find the action exempt from environmental review under the California Environmental Quality Act;
  • adopt the extension, with its findings; and
  • approve and issue the 10-Day Report that state law requires before the first ordinance expires.

The first ordinance, Ordinance 2026-08, was adopted on September 14 for 45 days and was set to expire on October 29. The September 14 minutes show all seven members voting yes: Mayor Greg Bozzo and Council Members Dion Bracco, Tom Cline, Terence Fugazzi, Zach Hilton, Carol Marques and Kelly Ramirez. An extension also needs a four-fifths vote, at least six of the seven. As of October 20 the city had not posted minutes, a vote tally or the numbered final ordinance for October 19; the vote reported here comes from the Spotlight. The extension takes effect at once.

What it covers

The ordinance continues a citywide pause on accepting, processing or approving any application, permit, license or other approval, ministerial or discretionary, for a new data center. Establishing one in violation is declared a public nuisance, and violations may be enforced by injunction or by administrative or criminal penalties under the city code.

It defines a data center as a facility, or a discrete part of one, designed, built or used as a stand-alone or primary use to house servers, data storage and the networking, cooling, electrical and backup power equipment that serves them, to store, process, manage or distribute data for one or more third parties or business units, including cloud, colocation and artificial intelligence uses, that either:

  • occupies 15,000 square feet or more of gross floor area; or
  • has, or is designed for, a dedicated critical information technology electrical load of one megawatt or more.

What it leaves out

  • The Amazon data center under construction. The ordinance does not apply to the Amazon Web Services facility at 8050 Camino Arroyo, a 56-acre site in the General Industrial (M2) zone, approved in its entirety on July 3, 2025, even where later phases are still being built.
  • Ordinary server rooms. A room, closet or other space that is accessory to a building's main use and supports only the occupant's own on-site operations is not a data center.
  • Approved projects. Work under an entitlement that was approved and in effect before the ordinance can continue.

Why the city acted

The staff reports and the ordinance's findings give these reasons:

  • No data center rules. Gilroy's zoning code does not treat data centers as a distinct use. They are allowed in the M2 zone under the general "Data Processing Establishments" category, so the Amazon project was approved administratively by the Community Development Director, with no hearing before the Planning Commission or council.
  • A second Amazon proposal. The city has received a pre-application from Amazon Web Services for a second data center at or near Highway 152 and Camino Arroyo. No formal application has been filed, and staff expect one, and possibly others from other operators.
  • The first project's record. The certified environmental impact report for the Camino Arroyo project found two impacts that remain significant after mitigation: the conversion of Prime Farmland and Farmland of Statewide Importance, and vehicle miles traveled. The ordinance cites up to 49 megawatts of electrical demand per building (98 megawatts for two), 25 diesel backup generators of 2.5 megawatts and one of 600 kilowatts for the first building alone, and water demand of up to about 7.49 million gallons (23 acre-feet) a year at full build-out.
  • Council direction. After extensive testimony on August 17, for and against the Amazon project, the council directed staff to bring back objective design standards for commercial and industrial projects.

The staff report also lists legal constraints: a federal data center bill package proposed in Congress and several state data center bills it says were recently signed. Amazon representatives have said the company is investing in local land conservation and water replenishment projects, using 100 percent carbon-free energy to power the data center, committing to 100 percent recycled water by 2030 and covering all infrastructure costs so residents do not bear them, according to the Spotlight.

Who it touches

  • Data center developers and landowners. No new data center application can be accepted or approved in Gilroy until the pause ends. The second Amazon proposal is held at the pre-application stage.
  • Industrial property owners and brokers. No site anywhere in the city, including the M2 zone where data centers are now allowed, can be entitled for a data center of the defined size during the pause.
  • Neighbors and the city's infrastructure. The standards being written address electrical grid capacity, water and cooling, generator emissions and noise, lighting, screening, truck traffic and decommissioning.
  • The city budget. The staff report says the work will take staff time and consultant resources and gives no dollar figure.

What happens next

  • The standards. The 10-Day Report says staff have begun reviewing other California cities' and counties' data center rules and the Amazon project's environmental report, and will define data centers as a use, decide which zones, if any, would allow them, and set the permit process and standards. That work needs coordination with utilities, environmental review, outreach and hearings before the Planning Commission and council. Staff plan to fold it into the city's comprehensive zoning code update and bring it back before or alongside that update. The aim is to have draft standards ready for review before the moratorium expires, the Spotlight reported.
  • Publication. The ordinance, or a summary, must be published once in a local newspaper within 15 days of adoption, by November 3.
  • Another report. State law requires a new written report 10 days before the extension expires, by August 24, 2027.
  • September 3, 2027. The extension expires unless the council extends it again. State law allows one more extension of one year, again by a four-fifths vote after notice and a hearing, and no more after that. The staff report says staff may need to ask for it.

For a nearby comparison, Santa Clara's council has asked its staff to speed up water and air standards for data centers (Santa Clara puts water and air standards for data centers first).

How to weigh in

Written comments on any agenda item go to the City Clerk's Office at publiccomment@cityofgilroy.org, or by mail to the Gilroy City Clerk's Office, City Hall, 7351 Rosanna Street, Gilroy, CA 95020; comments received by 1 p.m. on a meeting day go to the council before the meeting. The clerk's office is at (408) 846-0204 and cityclerk@cityofgilroy.org. Agendas, packets and video for council and Planning Commission meetings are posted at gilroyca.portal.civicclerk.com.